Disaster Recovery Cutover Plan 2025

About the DR Cutover Plan

The Disaster Recovery (DR) is an annual activity to ensure service continuity in the event of an unexpected outage or system failure. It involves transitioning operations from the primary region to a secondary region, known as failover, and then returning operations back to the primary region, known as failback.

In 2025, DR testing will be conducted across both UAT and Production environments. It includes two types of tests:

  • Weekend Tests
    A 24-hour testing window where users can connect and interact with DSB in a controlled DR environment.

  • Extended Tests
    A two-week period where the DSB operates entirely from the secondary region, allowing users to conduct business-as-usual during an extended DR scenario.

Notifications will be sent throughout the process to confirm when failover and failback activities begin and end. 

Why this matters:
These tests are critical to ensure business continuity, regulatory compliance, and ensuring that services remain available during a disruption.

Client Preparation and Required Actions

  • Users who access the DSB via published aliases do not need to take any action. However, users who have not previously participated in a DSB disaster recovery (DR) test should ensure that secondary IP addresses are properly configured within their networks.
  • Users who directly reference DSB’s IP addresses must update their configurations to align with the IP addresses associated with the DSB’s aliases.
  • Users are asked to test their connectivity once the related activities have been completed.
  • Users are also asked to review all notifications, which will outline the relevant processes and confirm the status of each activity.

Testing Schedule - UAT & Production

Test TypeEnvironmentStatusDescriptionStart Date/TimeEnd Date/Time
Weekend TestUATNot started24-hour DR testSat, 20 Sept 2025 1:30am BST, UTC+1Sun, 21 Sept 2025 1:30pm BST, UTC+1
Extended TestUATNot started2-week DR testSun, 5 Oct 2025 2:00am BST, UTC+1Sun, 19 Oct 2025 2:00am BST, UTC+1
Weekend TestProductionNot started24-hour DR testSat, 1 Nov 2025 1:30am BST, UTC+0Sun, 2 Nov 2025 1:30pm BST, UTC+0
Extended TestProductionNot started2-week DR testSat, 15 Nov 2025 1:00am BST, UTC+0Sat, 29 Nov 2025 2:00am BST, UTC+0

DR Notifications

DateTitle/SummaryLink 
 14 Jul 20252025-07-14 NOTIFICATION DSB 2025 Disaster Recovery Testing Timeline (UAT & Production)Link
 28 Jul 2025 2025-07-28 REMINDER NOTIFICATION DSB 2025 Disaster Recovery Testing Timeline (UAT & Production) Link